© 2012 SMS Siemag AG All rights reserved Reproduction only with the permission of SMS Siemag AG, Düsseldorf |
New rougher in just 18 days
Salzgitter Flachstahl, Germany. What made the revamp of the hot broad strip mill at Salzgitter Flachstahl GmbH even more impressive than usual were the extremely short stoppage times. The biggest challenge was installing the new rougher and the new edger in just 18 days. Simultaneously, we upgraded 5 of the 7 finishing stands with CVC® plus shifting systems and work roll bending. We not only revamped the mechanical systems, but also replaced the existing automation with our X-Pact® system. A new slab sizing press had already been installed previously.
Results of the revamp
![]() |
Increased production |
![]() |
Improved thickness tolerances |
![]() |
Improved width tolerances |
![]() |
Increased share of high-strength steels in the production mix |
Revamp stages
![]() |
New sizing press (2001) |
![]() |
New rougher with flange-attached edger (2003) |
![]() |
CVC® plus and work roll bending for F2 - F5 (2003) |
![]() |
New automation for roughing and finishing trains (2003) |